# The Mona Offshore Wind Farm Order 2025, Article 19: Compulsory acquisition of land

Extent: E+W

(1) The undertaker may acquire compulsorily so much of the Order land as is required for the authorised project or to carry out or to facilitate, or is incidental to it.
(2) This article is subject to:
(a) article 20 (time limit for exercise of authority to acquire land compulsorily);
(b) article 21 (compulsory acquisition of rights);
(c) article 25 (acquisition of subsoil only);
(d) article 27 (rights under or over streets);
(e) article 28 (temporary use of land for carrying out the authorised project)
(f) article 38 (crown rights); and
(g) article 39 (protective provisions).

---
Source: https://www.legislation.gov.uk/uksi/2025/870/article/19 (the official version)
Page: https://openlegislation.uk/mona-offshore-wind-farm-order-2025/article-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.