# The Mona Offshore Wind Farm Order 2025, Paragraph 11: Miscellaneous

Extent: E+W

Any difference or dispute arising between the undertaker and the affected undertaker under this Part must, unless otherwise agreed in writing between the undertaker and the affected undertaker, be determined by arbitration in accordance with article 45 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2025/870/schedule/10/paragraph/11 (the official version)
Page: https://openlegislation.uk/mona-offshore-wind-farm-order-2025/schedule-10/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.