# The Mona Offshore Wind Farm Order 2025, Paragraph 51: Approvals

Extent: E+W

The crossing of the A55 and its associated assets must only be carried out by trenchless techniques.

---
Source: https://www.legislation.gov.uk/uksi/2025/870/schedule/10/paragraph/51 (the official version)
Page: https://openlegislation.uk/mona-offshore-wind-farm-order-2025/schedule-10/paragraph-51
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.