# The Mona Offshore Wind Farm Order 2025, Paragraph 84: Mona project works

Extent: E+W

(1) Any approval of National Grid required under this Schedule—
(a) must not be unreasonably withheld or delayed;
(b) in the case of a refusal must be accompanied by a statement of grounds or refusal; and
(c) may be given subject to such reasonable requirements as National Grid may have in connection with the safe, economic and efficient construction, commissioning, operation, maintenance and future decommissioning of the Bodelwyddan Project and/or the Connah’s Quay Project or otherwise for the protection of Bodelwyddan apparatus and/or the Connah’s Quay apparatus,
() provided always that in relation to a refusal under sub-paragraph (b) or any requirements requested pursuant to sub-paragraph (c) the undertaker shall be permitted to refer such matters to dispute resolution pursuant to paragraph 98.
(2) National Grid must employ reasonable endeavours to respond to the submission of any plans within a period of 56 days from the date of submission of the plans. If National Grid require further particulars, such particulars must be requested by National Grid no later than 21 days from the submission of plans and thereafter National Grid must employ reasonable endeavours to respond to the submission within 56 days from receipt of the further particulars.

---
Source: https://www.legislation.gov.uk/uksi/2025/870/schedule/10/paragraph/84 (the official version)
Page: https://openlegislation.uk/mona-offshore-wind-farm-order-2025/schedule-10/paragraph-84
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.