{
  "url": "https://openlegislation.uk/mona-offshore-wind-farm-order-2025/schedule-10/paragraph-88",
  "json_url": "https://openlegislation.uk/mona-offshore-wind-farm-order-2025/schedule-10/paragraph-88.json",
  "legislation": "uksi/2025/870",
  "legislation_title": "The Mona Offshore Wind Farm Order 2025",
  "legislation_url": "https://openlegislation.uk/mona-offshore-wind-farm-order-2025",
  "path": "schedule/10/paragraph/88",
  "kind": "paragraph",
  "number": "88",
  "heading": "Protective works to buildings",
  "text": "The undertaker, in the case of the powers conferred by article 18 (protective work to buildings), must exercise those powers so as not to obstruct or render less convenient the access to any apparatus, the Bodelwyddan Site and/or the Connah’s Quay Site without the written consent of National Grid Electricity Transmission Plc which will not unreasonably be withheld.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 10 para. 88 in force at 28.7.2025, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2025/870/schedule/10/paragraph/88",
    "retrieved_at": "2026-10-28T21:13:09.870071+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}