# The Mona Offshore Wind Farm Order 2025, Paragraph 99: Notices

Extent: E+W

Notwithstanding article 42 (service of notices), any plans submitted to National Grid Electricity Transmission Plc by the undertaker pursuant to paragraph 92 must be submitted using the LSBUD system (https://lsbud.co.uk/) or to such other address as National Grid Electricity Transmission Plc may from time to time appoint instead for that purpose and notify to the undertaker in writing.

---
Source: https://www.legislation.gov.uk/uksi/2025/870/schedule/10/paragraph/99 (the official version)
Page: https://openlegislation.uk/mona-offshore-wind-farm-order-2025/schedule-10/paragraph-99
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.