# The Mona Offshore Wind Farm Order 2025, Paragraph 18: Pre-construction plans and documentation

Extent: E+W

(1) Each programme, statement, plan, protocol or scheme required to be approved under condition 17 must be submitted for approval at least four months before the intended commencement of licensed marine activities, except where otherwise stated or unless otherwise agreed in writing by the licensing authority.
(2) The licensed marine activities must be carried out in accordance with the plans, protocols, statements, schemes and details approved under condition 17, unless otherwise agreed in writing by the licensing authority.

---