# The Mona Offshore Wind Farm Order 2025, Paragraph 4: Stages of authorised project

Extent: E+W

(1) No stage of the onshore works may commence until notification has been submitted to the relevant planning authority detailing whether the onshore works will be constructed:
(a) in a single stage; or
(b) in two or more stages.
(2) No stage of the onshore works may commence until details of the stages of the onshore works have been submitted to and approved in writing by the relevant planning authority.
(3) The stages of the onshore works must be implemented as approved.

---