# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 10: Decommissioning

Extent: E+W+S

No part of the authorised development may commence until a written decommissioning programme in compliance with any notice served upon the undertaker by the Secretary of State pursuant to section 105(2) (requirement to prepare decommissioning programmes) of the 2004 Act has been submitted to ... the Secretary of State for approval.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/2/paragraph/10 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-2/paragraph-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.