# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 1: Application

Extent: E+W+S

For the protection of the owners from time to time of the Calder Field which at the date stated in article 1 (citation and commencement) of this Order is Harbour Energy, unless otherwise agreed in writing between the undertaker and the owner the provisions of this Part of this Schedule shall have effect until completion of all activities required under any statutory decommissioning plan required under the Petroleum Act 1998 in relation to the Calder Field.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/3/part/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-3/part-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.