# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 6: Coexistence agreement

Extent: E+W+S

Prior to the commencement of construction of the authorised development, the undertaker and the owner shall use reasonable endeavours to enter into a coexistence agreement (which includes provision for proximity agreements on standard UK oil and gas industry terms and arrangements for coordinating marine access and simultaneous operations).

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/3/part/2/paragraph/6 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-3/part-2/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.