# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 6


Without prejudice to any other rights or obligations under this Part of this Schedule the licensee and the undertaker shall as soon as reasonably practicable following a request provide to the other programme information in relation to their development proposals and activities within or adjacent to the Order limits or any buffer zone and from time to time keep each other informed of any revisions to the previously provided programme such that the licensee and the undertaker may seek to agree solutions to allow those activities to successfully co-exist as far as reasonably practicable.

---