# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 5: Vessel Traffic Management Plan

Extent: E+W+S

The undertaker must consult Stena Line before submitting the vessel traffic management plan to any licensing authority and the undertaker must have regard to any response received from Stena Line in respect of the vessel traffic management plan.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/3/part/6/paragraph/5 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-3/part-6/paragraph-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.