# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 2: Applications made under requirements

Extent: E+W+S

(1) Where an application has been made to the discharging authority for any agreement or approval required pursuant to a requirement included in this Order, the discharging authority must give notice to the undertaker of their decision on the application, including the reasons for that decision, within a period of eight weeks beginning with—
(a) the day immediately following that on which the application is received by the discharging authority; or
(b) where further information is requested under paragraph 3 the working day immediately following that on which the further information has been supplied by the undertaker, or such longer period as may be agreed by the undertaker and the discharging authority.
(2) Where consent, agreement or approval is refused or granted subject to conditions the discharging authority must provide its reasons for that decision with the notice of the decision.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/4/paragraph/2 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-4/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.