# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 17: Reporting of scour and cable protection

Extent: E+W+S

(1) Not more than four months following completion of the construction of the authorised project, the undertaker must provide the MMO and the relevant statutory nature conservation body with a report setting out details of the cable protection and scour protection used for the authorised project.
(2) The report must include the following information—
(a) the location of cable protection and scour protection;
(b) the volume of cable protection and scour protection; and
(c) any other information relating to the cable protection and scour protection as agreed between the MMO and the undertaker.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/6/paragraph/17 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-6/paragraph-17
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.