# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 18: Completion of construction

Extent: E+W+S

(1) The undertaker must submit a close-out report to the MMO, MCA, Trinity House, the UKHO and the relevant statutory nature conservation body within four months of the date of completion of construction. The close out report must confirm the date of completion of construction and must include the following details—
(a) the final number of installed wind turbine generators;
(b) the installed wind turbine generator parameters relevant for ornithological collision risk modelling;
(c) as built plans;
(d) latitude and longitude coordinates of the centre point of the location for each wind turbine generator and offshore substation platform provided as Geographical Information System data referenced to WGS84 datum; and
(e) latitude and longitude coordinates of the inter array cables and platform link cable routes provided as Geographical Information System data referenced to WGS84 datum.
(2) Following completion of construction, no further construction activities can be undertaken under this licence.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/6/paragraph/18 (the official version)