(1) In the event that driven or part-driven pile foundations are proposed to be used as part of the foundation installation, the undertaker must provide the following information to the Marine Noise Registry—
(a) no less than six months prior to the commencement of each stage of construction of the licensed activities, information on the expected location, start and end dates of impact pile driving to satisfy the Marine Noise Registry’s forward look requirements;
(b) within two weeks after commencement of each stage of construction of the licensed activities, information on the location, start and end dates of impact pile driving to satisfy the Marine Noise Registry’s forward look requirements; and
(c) at six month intervals following the commencement of pile driving, information on the locations and dates of impact pile driving to satisfy the Marine Noise Registry’s close out requirements by 7 April for the winter season (October to March inclusive) and 7 October for the summer season (April to September inclusive) or within 12 weeks of completion of impact pile driving, whichever is earlier.
(2) For the purpose of this condition—
“Marine Noise Registry” means the database of impulsive noise generating activities in UK seas maintained by the Joint Nature Conservation Committee or any successor database; and
“forward look” and “close out” requirements are as set out in the “UK Marine Noise Registry: Information Document, Version 1 (May 2016)” or any updated information document.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/6/paragraph/19 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-6/paragraph-19
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.