# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 21: Deployment of new cable protection and scour protection

Extent: E+W+S

Any cable protection and scour protection (other than the replenishment or replacement of existing cable protection or scour protection) authorised under this licence must be deployed within ten years from the date on which operation of the authorised project commences unless otherwise agreed by the MMO.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/6/paragraph/21 (the official version)