# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 2

Extent: E+W+S

No later than six months prior to the commencement of the authorised development, the undertaker must confirm in writing to the Secretary of State that—
(a) it intends to make a Marine Recovery Fund Payment wholly in substitution for the lesser black-backed gull compensation measure and that it has received confirmation from Defra or the Marine Recovery Fund operator that suitable measures are available; or
(b) it intends to submit a final lesser black-backed gull CIMP to the Secretary of State for approval.

---