# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 6

Extent: E+W+S

The final lesser black-backed gull CIMP, if required, must be based on the strategy for lesser black-backed gull compensation set out in the outline compensation implementation and monitoring plan and must include—
(a) details of the location(s) where the lesser black-backed gull compensation measure will be delivered;
(b) details of how any necessary land access rights, licences and approvals have been or will be obtained;
(c) an implementation timetable for delivery of the lesser black-backed gull compensation measure;
(d) a record of LBBGCSG consultations;
(e) details of the proposed ongoing monitoring and reporting on the effectiveness of the lesser black-backed gull compensation measure, including—
(i) survey methods;
(ii) success criteria;
(iii) adaptive management measures;
(iv) timescales for the monitoring and monitoring reports to be delivered; and
(v) details of the mechanism to determine the need for any alternative compensation measures or implementation of adaptive management measures (or both).

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/7/part/1/paragraph/6 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-7/part-1/paragraph-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.