No WTG forming part of Work No. 1 may commence operation until the lesser black-backed gull compensation measure has been implemented for four breeding seasons, unless commencement of operation at an earlier date is approved by the Secretary of State. For the purposes of this paragraph each breeding season is 1 March to 30 September of each year inclusive.

---