# The Morecambe Offshore Windfarm Generation Assets Order 2025, Paragraph 11

Extent: E+W+S

The habitat management measure as approved in the final red-throated diver CIMP must be maintained by the undertaker (or at the undertaker’s expense) for the operational lifetime of the WTGs erected under Work No. 1 and must not be decommissioned without the written approval of the Secretary of State in consultation with the relevant statutory nature conservation body.

---
Source: https://www.legislation.gov.uk/uksi/2025/1366/schedule/7/part/2/paragraph/11 (the official version)
Page: https://openlegislation.uk/morecambe-offshore-windfarm-generation-assets-order-2025/schedule-7/part-2/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.