# The Morgan Offshore Wind Project Generation Assets Order 2025, Article 5: Deemed marine licences under the 2009 Act

Extent: E+W

The marine licences set out in Schedules 3 and 4 are deemed to have been granted to the undertaker under Part 4 (marine licensing) of the 2009 Act for the licensed activities specified in Part 1 of each licence and subject to the conditions specified in Part 2 of each licence.

---
Source: https://www.legislation.gov.uk/uksi/2025/1012/article/5 (the official version)
Page: https://openlegislation.uk/morgan-offshore-wind-project-generation-assets-order-2025/article-5
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.