# The Morgan Offshore Wind Project Generation Assets Order 2025, Paragraph 11: Design parameters

Extent: E+W

The total number of offshore substation platforms forming part of the authorised scheme in this licence and the authorised scheme in licence 1 taken together must not exceed four (whether constructed under this licence or licence 1).

---
Source: https://www.legislation.gov.uk/uksi/2025/1012/schedule/4/paragraph/11 (the official version)
Page: https://openlegislation.uk/morgan-offshore-wind-project-generation-assets-order-2025/schedule-4/paragraph-11
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.