Part 4 Documents to be submitted and approved by the Welsh Ministers
| (1) | (2) |
|---|---|
| Document | To be approved prior to these actions |
| Cable Management Plan | Prior to the commencement of any related tidal works |
| Construction Environmental Management Plan | Prior to the commencement of any related tidal works |
| Decommissioning Programme | Prior to the decommissioning of any related tidal works |
| Detailed marine biodiversity enhancement strategy | Prior to each of the following activities:
|
| Device Deployment Protocol | Prior to the deployment of any tidal device or operational hub which will be—
|
| Environmental Mitigation and Monitoring Plan | Prior to each of the following activities—
|
| Identification of Archaeological Exclusion Zones | Prior to the commencement of any related tidal works |
| Installation Methodology | Prior to the commencement of any related tidal works where trenching is required for laying of cables |
| Marine Mammal Mitigation Protocol | Prior to each of the following activities—
|
| Marine Pollution Contingency Plan | Prior to the commencement of any related tidal works |
| Updated Navigational Risk Assessment | Prior to each of the following activities—
|
| Pollution Prevention and Management Plan | Prior to the commencement of any related tidal works |