# The National Grid (Bramford to Twinstead Reinforcement) Order 2024, Article 58: Arbitration

Extent: E+W

(1) Subject to article 51 (procedure regarding certain approvals, etc.) and except where otherwise expressly provided for in this Order or unless otherwise agreed between the parties, any difference under any provision of this Order must be referred to and settled by a single arbitrator to be agreed between the parties or, failing agreement, to be appointed on the application of either party (after giving notice in writing to the other) by the Secretary of State.
(2) Any matter for which the consent or approval of the Secretary of State is required under any provision of this Order shall not be subject to arbitration.

---
Source: https://www.legislation.gov.uk/uksi/2024/958/article/58 (the official version)
Page: https://openlegislation.uk/national-grid-bramford-to-twinstead-reinforcement-order-2024/article-58
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.