  "url": "https://openlegislation.uk/national-grid-bramford-to-twinstead-reinforcement-order-2024/article-8",
  "json_url": "https://openlegislation.uk/national-grid-bramford-to-twinstead-reinforcement-order-2024/article-8.json",
  "legislation": "uksi/2024/958",
  "legislation_title": "The National Grid (Bramford to Twinstead Reinforcement) Order 2024",
  "legislation_url": "https://openlegislation.uk/national-grid-bramford-to-twinstead-reinforcement-order-2024",
  "path": "article/8",
  "kind": "article",
  "number": "8",
  "heading": "Application of the 1990 Act",
  "text": "(1) In respect of the temporary construction works, section 57(2) of the 1990 Act (planning permission required for development) applies as if the development consent granted by this Order were planning permission granted for a limited period.\n(2) Development consent granted by this Order is to be treated as specific planning permission for the purposes of section 264(3)(a) of the 1990 Act (cases in which land is to be treated as not being operational land).\n(3) In the exercise of the power under paragraphs (1) and (2) of article 11 (street works) the undertaker is to be deemed to be the highway authority for the purposes of section 55(2)(b) of the 1990 Act.",
  "extent": "E+W",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Art. 8 in force at 4.10.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/958/article/8",
    "retrieved_at": "2026-10-28T21:26:26.573366+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}