# The National Grid (Bramford to Twinstead Reinforcement) Order 2024, In the Districts of Mid-Suffolk, Babergh and Braintree

Extent: E+W

Works as shown on Sheets 4, 5, 7 to 17 (inclusive), 19, 20, 21 and 22 of the work plans to allow the removal of 25 kilometres of the existing overhead distribution electric line (Route PCB) between Burstall Bridge at a point indicated as PCB5 and a point to the west of Twinstead Tee indicated as PCB89, including—
(a) the modification of existing pylons PCB5 and PCB89;
(b) the dismantling and removal of all overhead distribution electric line and pylons including foundations between Burstall Bridge commencing at a point indicated as PCB5 on Sheet 4 of the work plans (but not including pylon PCB5) and terminating at a point to the west of Twinstead Tee indicated as PCB89 on Sheet 22 of the work plans (but not including pylon PCB89); and
(c) the dismantling and removal of conductors, insulators and fittings.

---
Source: https://www.legislation.gov.uk/uksi/2024/958/schedule/1/crossheading/distribution-electric-line-in-the-districts-of-midsuffolk-babergh-and-braintree (the official version)
Page: https://openlegislation.uk/national-grid-bramford-to-twinstead-reinforcement-order-2024/schedule-1/crossheading-distribution-electric-line-in-the-districts-of-midsuffolk-babergh-and-braintree
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.