# The National Grid (Bramford to Twinstead Reinforcement) Order 2024, Paragraph 47

Extent: E+W

The undertaker must no later than 28 days from the date that the plans submitted to and certified by the Secretary of State in accordance with article 56 (certification of documents) are certified by the Secretary of State, provide a set of those plans to Network Rail in a format specified by Network Rail.

---