# The National Grid (Bramford to Twinstead Reinforcement) Order 2024, Paragraph 2

Extent: E+W

(1) The authorised development must commence no later than the expiration of five years beginning with the date on which this Order comes into force.
(2) If any proceedings are begun to challenge the validity of this Order, the period specified in paragraph (1) is extended for the period specified in paragraph (3).
(3) Under paragraph (2) the period is taken to be extended by—
(a) a period equivalent to the period beginning with the day the proceedings are filed and ending on the day they are withdrawn or finally determined, or
(b) if shorter, one year.
(4) Proceedings are not finally determined for the purposes of sub-paragraph (3)(a) if any appeal—
(a) could be brought (ignoring any possibility of an appeal out of time with permission), or
(b) has been made and not withdrawn or finally determined.

---
Source: https://www.legislation.gov.uk/uksi/2024/958/schedule/3/paragraph/2 (the official version)
Page: https://openlegislation.uk/national-grid-bramford-to-twinstead-reinforcement-order-2024/schedule-3/paragraph-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.