# The National Grid (Bramford to Twinstead Reinforcement) Order 2024, Paragraph 3

Extent: E+W

(1) Unless otherwise agreed with the relevant planning authority, written notice setting out the anticipated programme for the carrying out of pre-commencement operations must be given to the relevant planning authority no less than seven days prior to the date on which those pre-commencement operations are first carried out.
(2) The authorised development may not commence until a written scheme setting out all stages of the authorised development has been submitted to the relevant planning authority.
(3) Any revisions to the written scheme referred to in sub-paragraph (2) above must be submitted to the relevant planning authority in advance of the commencement of the stage of the authorised development to which the revisions relate.
(4) Written notice of the commencement and completion of construction of each stage of the authorised development, and the operational use of each stage of the authorised development, must be given to the relevant planning authority within ten business days of the relevant event occurring.
(5) The authorised development must be carried out in accordance with the written scheme submitted further to sub-paragraph (2) or (3) and, to the extent applicable, in general accordance with the written notice submitted further to sub-paragraph (1).

---
Source: https://www.legislation.gov.uk/uksi/2024/958/schedule/3/paragraph/3 (the official version)
Page: https://openlegislation.uk/national-grid-bramford-to-twinstead-reinforcement-order-2024/schedule-3/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.