(1) Where an application is made to a relevant authority for any consent, agreement or approval required by a requirement (including consent, agreement or approval in respect of part of a requirement), a fee must be paid to the relevant authority as follows—
(a) such fee as may be prescribed (under sections 303 and 333(2A) of the 1990 Act for the discharge of conditions attached to a planning permission); or
(b) a fee of £145 per request unless a bespoke arrangement has been agreed between the Applicant and discharging authority and legally secured.

---