# The National Grid (Bramford to Twinstead Reinforcement) Order 2024, Part 2: STREETS SUBJECT TO TEMPORARY ALTERATION OF LAYOUT

Extent: E+W

SUFFOLK COUNTY COUNCIL
(1)
Street subject to alteration of layout
(2)
Description of alteration of layout as shown on the Access, Rights of Way and Public Rights of Navigation Plans
Bullen Lane
At access point AB-AP1 a temporary bellmouth will be created (as shown on Sheet 1) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Burstall Hill
At access points AB-AP2A and AB-AP2B, two temporary bellmouths will be created (as shown on Sheets 1 and 2) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Church Hill
At access point AB-AP3, AB-AP4, AB-AP5, three temporary bellmouths will be created (as shown on Sheet 2) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
A1071 (Back Road)
At access points AB-AP6, AB-AP7, AB-AP8, AB-EAP1 and AB-EAP2a, five temporary bellmouths will be created (as shown on Sheets 3 and 6) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
A1071 (Ipswich Road)
At access point AB-EAP2b a temporary bellmouth will be created (as shown on Sheet 6) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
A1071 (Hadleigh Road)
At access point AB-DAP1 a temporary bellmouth will be created (as shown on Sheet 4) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Washbrook Road
At access points AB-DAP2, AB-DAP3, two temporary bellmouths will be created (as shown on Sheet 4) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Lower Barn Road
At access point AB-DAP4 a temporary bellmouth will be created (as shown on Sheet 5) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Mill Lane
At access point AB-DAP5 a temporary bellmouth will be created (as shown on Sheet 5) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Duke Street
At access point AB-DAP6 a temporary bellmouth will be created (as shown on Sheet 7) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Clay Hill
At access point AB-DAP7 a temporary bellmouth will be created (as shown on Sheet 7) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Pond Hall Road
At access points AB-DAP8, AB-AP9, AB-AP11, AB-AP12, AB-AP13, AB-AP14, AB-AP17, seven temporary bellmouths will be created (as shown on Sheets 7 to 9) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Woodlands Road
At access point AB-DAP9 a temporary bellmouth will be created (as shown on Sheet 8) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Clay Lane
At access points AB-DAP10, AB-AP15, AB-AP16, three temporary bellmouths will be created (as shown on Sheet 8) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
B1070 (Pipkin Hill)
At access points C-AP1 and C-AP2, two temporary bellmouths will be created (as shown on Sheet 10) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
B1070 (The Street)
At access point C-DAP1 a temporary bellmouth will be created (as shown on Sheet 10) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Layham Road
At access points C-AP3, C-AP4, two temporary bellmouths will be created (as shown on Sheet 10) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Overbury Hall Road
At access points C-AP5, D-AP1, two temporary bellmouths will be created (as shown on Sheet 11) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Rands Road
At access points D-DAP1, D-AP2, two temporary bellmouths will be created (as shown on Sheet 11) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Millwood Road
At access points D-AP3, D-AP4, two temporary bellmouths will be created (as shown on Sheet 12) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Heath Road
At access points D-AP6, D-AP7, D-DAP2A, D-DAP3, four temporary bellmouths will be created (as shown on Sheet 12) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Holt Road
At access points D-AP8, E-AP1, two temporary bellmouths will be created (as shown on Sheet 13) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Whitestreet Green
At access points E-AP4, E-AP5, E-AP6, E-DAP2, E-DAP3, five temporary bellmouths will be created (as shown on Sheets 13 and 14) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Brick Kiln Hill
At access points E-AP8, F-DAP1, two temporary bellmouths will be created (as shown on Sheet 15) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
B1068 (Stoke Road)
At access points E-AP7, E-DAP4, E-DAP5, F-AP1 and at points BM-1 and BM-2, six temporary bellmouths will be created (as shown on Sheet 15) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required. Note: points BM-1 and BM-2 have no associated construction traffic, they are only used as crossing points.
Colchester Road (A134)
At access points F-AP5, F-AP6, F-AP7, F-DAP2, four temporary bellmouths will be created (as shown on Sheets 15 and 16) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Nayland Road
At access points F-AP8, F-AP9, F-DAP3, three temporary bellmouths will be created (as shown on Sheet 16) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Bures Road
At access points F-AP10, F-AP12, F-AP13, F-DAP4, F-DAP5, five temporary bellmouths will be created (as shown on Sheet 17) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Wormingford Road
At access point F-AP11 a temporary bellmouth will be created (as shown on Sheet 17) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Dorking Tye
At access points F-AP14, G-AP1, G-AP2 three temporary bellmouths will be created (as shown on Sheets 17) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
B1508 (St Edmunds Hill)
At access points G-AP4, G-DAP1, G-DAP2, three temporary bellmouths will be created (as shown on Sheet 20) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
ESSEX COUNTY COUNCIL
(1)
Street subject to alteration of layout
(2)
Description of alteration of layout as shown on the Access, Rights of Way and Public Rights of Navigation Plans
Henny Road
At access points G-AP5, G-AP6, G-DAP3, G-DAP4, four temporary bellmouths will be created (as shown on Sheet 20) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Losh House Lane
At access points G-AP9, G-AP13, two temporary bellmouths will be created (as shown on Sheet 21) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Twinstead Road
At access points G-DAP5, G-DAP6, G-DAP7, G-DAP8, four temporary bellmouths will be created (as shown on Sheets 21 and 27) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Lorkin’s Lane
At access point G-AP10 a temporary bellmouth will be created (as shown on Sheets 21 and 27) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Clay Hill
At access point G-YLAP3 a temporary bellmouth will be created (as shown on Sheet 22) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Church Road
At access point G-YLAP4 a temporary bellmouth will be created (as shown on Sheet 22) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Watery Lane
At access point G-YLAP5 a temporary bellmouth will be created (as shown on Sheet 22) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Rectory Lane
At access point H-YLAP2 a temporary bellmouth will be created (as shown on Sheet 24) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Church Road
At access points H-YLAP3, H-YLAP4, two temporary bellmouths will be created (as shown on Sheet 24) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Hedingham Road
At access points H-YLAP5, H-YLAP6, two temporary bellmouths will be created (as shown on Sheet 24) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Old Road
At access points H-AP3, H-AP4, H-AP5, H-AP6, H-AP7, H-YLAP1, six temporary bellmouths will be created (as shown on Sheets 23 and 26) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Park Road
At access point H-AP8 a temporary bellmouth will be created (as shown on Sheet 26) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Moat Lane
At access points G-AP7, G-AP8, two temporary bellmouths will be created (as shown on Sheet 27) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Henny Back Road
At access points G-AP11, G-AP12, G-AP15, H-AP10, H-AP11, five temporary bellmouths will be created (as shown on Sheet 28) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Whitelands Road
At access points H-AP12, H-AP13, H-AP16 and H-AP17, four temporary bellmouths will be created (as shown on Sheet 29) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Lorkin’s Lane
At access points H-AP14, H-AP15, two temporary bellmouths will be created (as shown on Sheet 29) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Oak Road
At access points H-AP18, H-AP19, two temporary bellmouths will be created (as shown on Sheet 29) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.
Sudbury Road (A131)
At access point H-AP20 a temporary bellmouth will be created (as shown on Sheet 30) to enable access/egress with sufficient size to accommodate a HGV vehicle. Comprising the installation of a new road surface, road markings, kerbing and a suitable drainage system, where required.

---
Source: https://www.legislation.gov.uk/uksi/2024/958/schedule/6/part/2 (the official version)
Page: https://openlegislation.uk/national-grid-bramford-to-twinstead-reinforcement-order-2024/schedule-6/part-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.