Article 2 Corrections
In Schedule 15 (Protective Provisions), Part 5 (Protection for First Corporate Shipping Limited) to the National Grid (Hinkley Point C Connection Project) Order 2016 (“the Order”), after paragraph 61 (BPC’s apparatus) insert—
“Acquisition and use of land
61A.The undertaker must not exercise the powers conferred by—
(a)article 17 (protective work to buildings);
(b)article 19 (compulsory acquisition of land);
(c)article 22 (compulsory acquisition of rights);
(d)article 23 (extinguishment and suspension of private rights);
(e)article 26 (acquisition of subsoil or airspace only);
(f)article 28 (rights under or over streets); or
(g)article 31 (temporary use of land for maintaining the authorised development),
over or in respect of any of BPC’s land unless the exercise of such powers is with the consent of BPC.
Procedure regarding certain approvals etc.