# The National Grid (Hinkley Point C Connection Project) Order 2016, Article 20: Compulsory acquisition of land – incorporation of the mineral code


Parts 2 and 3 of Schedule 2 to the Acquisition of Land Act 1981 (minerals) are incorporated into this Order subject to the modifications that—
(a) paragraph 8(3) is not incorporated; and
(b) for “the acquiring authority” there is substituted “the undertaker”.

---
Source: https://www.legislation.gov.uk/uksi/2016/49/article/20 (the official version)
Page: https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016/article-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.