  "url": "https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016/schedule-12/part-2",
  "json_url": "https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016/schedule-12/part-2.json",
  "legislation": "uksi/2016/49",
  "legislation_title": "The National Grid (Hinkley Point C Connection Project) Order 2016",
  "legislation_url": "https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016",
  "path": "schedule/12/part/2",
  "kind": "part",
  "number": "2",
  "heading": "WESTERN POWER DISTRIBUTION",
  "text": "Sedgemoor District Council – Section A\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n1, 3, 4, 6, 7, 8, 9, 14, 15, 19, 29, 34, 35, 36, 41, 50, 56, 60, 61, 63, 64, 65, 70, 71, 74, 81, 82, 88, 91 & 94\nDismantling of redundant infrastructure\nWork No. 4B\n2, 5, 10, 16, 23, 28, 33, 40, 47, 53, 54, 62, 75, 78, 83, 84, 89, 90 & 93\nDismantling of redundant infrastructure\nWork No. 4B\nRemoval of pylon foundations only to a depth of 1 metre\n11, 12, 13, 17, 18, 20, 21, 22, 24, 25, 26, 27, 30, 31, 32, 37, 38, 39, 42, 43, 44, 45, 46, 48, 49, 51, 52, 55, 57, 58, 59, 66, 67, 68, 69, 72, 73, 76, 77, 79, 80, 85, 86, 87, 92, 97, 98, 101, 157 & 158\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\nSedgemoor District Council – Section B\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n4, 8, 9, 14, 36, 38, 39, 78, 84, 120, 125, 126, 127, 131, 132, 133, 134, 142, 153, 159, 160, 167, 171, 172, 174, 177.2, 178, 186, 187, 190, 193, 194, 251, 252, 253, 254, 273, 274, 278, 279, 281, 286, 371, 378, 380, 383, 385, 392, 394, 399, 400, 401, 402, 403, 404, 407, 411, 412, 417, 420, 421, 422, 423, 425, 434, 455, 462, 463, 465, 470, 471, 472, 476, 481, 485, 491, 494, 495, 498, 499, 500, 513, 514, 528, 530, 531, 532, 533, 534, 538, 540, 542, 543, 546, 547, 548, 551, 560, 572, 579, 587, 588, 589, 602, 603.2, 603.3, 604.2, 615, 619, 625, 626, 630, 631, 660, 666, 677 & 678\nDismantling of redundant infrastructure\nWork No. 4B\n5, 12, 15, 37, 76, 81, 86, 119, 135, 140, 151, 170, 177.1, 179, 185, 188, 191, 266, 269, 271, 272, 277, 280, 285, 288, 370, 386, 393, 397, 406, 408, 413, 419, 424, 426, 454, 461, 477, 482, 492, 501, 510, 527, 535, 537, 545, 558, 568, 578, 591, 603.1, 604.1, 611, 612, 620, 627, 641, 654, 659 & 676\nDismantling of redundant infrastructure\nWork No. 4B\nRemoval of pylon foundations only to a depth of 1 metre\n10, 11, 13, 16, 17, 18, 19, 20, 22, 23, 24, 34, 40, 42, 45, 46, 73, 79, 80, 82, 83, 115, 118, 121, 122, 129, 130, 138, 139, 154, 156, 165, 166, 168, 169, 173, 175, 176, 180, 181, 182, 183, 184, 189, 192, 255, 256, 257, 258, 259, 260, 261, 262, 263, 264, 265, 267, 268, 270, 275, 276, 282, 283, 284, 287, 359, 368, 373, 381, 384, 388, 391, 395, 396, 398, 405, 409, 410, 414, 415, 416, 418, 427, 428, 429, 433, 435, 437, 439, 450, 459, 460, 464, 466, 469, 478, 479, 480, 483, 484, 486, 488, 489, 490, 496, 502, 503, 504, 506, 507, 508, 509, 511, 512, 515, 516, 518, 520, 525, 526, 536.1, 536.2, 539, 541, 544, 549, 550, 556, 559, 562, 569, 581, 582, 584, 586, 593, 595, 596, 597, 599, 609.1, 609.2, 609.3, 609.4, 614, 616, 617, 618, 621, 622, 623, 624, 632, 633, 634, 640, 642, 643, 644, 649, 650.1, 650.2 , 652, 653, 665, 675, 679, 681 & 682\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\nSedgemoor District Council and North Somerset Council – Section B\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n664\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\nSedgemoor District Council – Section C\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n1 & 2\nDismantling of redundant infrastructure\nWork No. 4B\n6, 13, 15 & 19\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\n14 & 18\nDismantling of redundant infrastructure\nWork No. 4B\nRemoval of pylon foundations only to a depth of 1 metre\nSedgemoor District Council and North Somerset Council – Section C\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n25\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\n29 & 30\nDismantling of redundant infrastructure\nWork No. 4B\nNorth Somerset Council – Section C\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n33, 34, 37, 42, 43, 44, 47, 53, 56, 61, 64, 65, 66, 67, 71, 76, 77, 78, 91, 96, 99, 106, 107, 114, 115, 117, 119, 122, 123, 125, 128, 129, 132, 134, 139, 145, 146, 154, 160, 161, 162, 167, 168, 171, 172, 176, 181, 182, 183, 184, 185, 186, 196, 202.1, 202.2, 204, 208, 210, 211, 219, 220, 221, 225, 233, 234, 249, 255, 256, 257, 267, 268, 273, 274, 277, 280 & 281\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\n41, 51, 58, 59, 62, 83, 84, 85, 86, 88, 89, 93, 94, 98, 108, 111, 136, 137, 152, 153, 156, 157, 166, 180, 187, 188, 189, 190, 191, 207, 212, 213, 214, 215, 216, 227, 228, 231, 252, 253, 271, 276, 282, 283, 284 & 285\nDismantling of redundant infrastructure\nWork No. 4B\n50, 68, 112, 116, 147, 158, 159, 169, 205, 206, 209, 217, 240, 242, 244, 247, 248, 251 & 272\nDismantling of redundant infrastructure\nWork No. 4B\nRemoval of pylon foundations only to a depth of 1 metre\nNorth Somerset Council – Section D\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n3, 15 & 57\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWorks Nos. 4B and 4C\n4\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWorks Nos. 4A and 4B\n7, 8, 9, 11, 12, 13, 17, 52, 53, 54, 55, 56, 61, 66, 68, 75, 88, 89, 112.1, 112.2, 112.3, 115, 117, 118, 188, 189, 190, 196, 197, 203, 204, 205, 210, 211, 213, 229, 231, 237.1, 237.2, 240, 243, 248, 249, 251, 253, 254, 255, 278, 279, 283, 284, 285, 286, 289, 290, 296, 304, 306, 318.1, 318.2, 319, 321, 329, 341, 348, 349, 351, 352, 367, 372, 394, 416, 419, 422, 424, 434, 452, 453, 467, 484, 485, 492, 504, 506, 514, 517, 529, 544.1, 544.2, 548, 557, 558, 559, 560, 561, 566, 567, 571, 572, 574, 575, 591, 592, 593, 594, 595, 602, 604, 605, 611, 612, 613, 615, 616, 620, 621, 623, 672, 674, 675, 677, 678, 775, 776, 828, 900, 901, 902, 904, 961, 962, 963, 964, 965, 966, 967, 968, 969 & 970\nDismantling of redundant infrastructure\nWork No. 4B\n10, 62, 76, 106, 187, 194, 198, 199, 212, 232, 236, 247, 252, 288, 297, 308, 339, 345, 361, 371, 391, 413, 430, 438, 455, 464, 494, 511, 521, 522, 530, 545, 573, 596, 606, 617, 622, 673, 827, 832 & 903\nDismantling of redundant infrastructure\nWork No. 4B\nRemoval of pylon foundations only to a depth of 1 metre\n18 & 20\nConstruction of authorised development\nWorks Nos. 4B and 4C\n19\nConstruction of authorised development\nWorks Nos. 4B and 4C\nRemoval of pylon foundations only to a depth of 1 metre\n21, 23, 24, 27, 28, 29, 31, 33.1, 33.2 , 34, 35, 40, 41, 42, 43, 44, 45, 46 & 48\nConstruction of authorised development\nWork No. 4C\n22, 30, 38 & 39\nDismantling of redundant infrastructure\nWork No. 4C\n25 & 47\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4C\n26 & 32\nConstruction of authorised development\nWork No. 4C\nRemoval of pylon foundations only to a depth of 1 metre\n63, 67, 69, 74.1, 74.2, 74.3, 74.4, 74.5 77, 83, 86, 87, 102, 200, 208, 217, 218, 219, 220.1, 220.2, 221, 223, 224, 225, 226, 227, 228, 233, 234, 235, 241, 242, 244, 245, 246, 250, 257, 258.1, 258.2 , 262, 263, 264, 265, 267, 268, 269.1, 269.2 , 270.1, 270.2, 271, 272, 274, 277, 280, 282, 287, 291, 292, 293, 294, 295, 299.1, 299.2, 301.1, 301.2, 302, 303, 305.1, 305.2, 307, 311, 315.1, 315.2, 316, 317, 320, 322, 323, 324, 325, 332.1, 332.2, 333, 336, 337, 338, 340, 343, 344, 346, 350, 354, 355, 356, 357.1, 357.2, 358, 359, 362, 363, 364, 365, 366, 369, 370, 373, 376, 377, 378, 383, 384, 385, 386, 387, 388, 390, 392, 393, 395, 396, 397, 398, 399, 400.1, 400.2 , 402, 407, 408.1, 408.2, 409, 410, 411, 414, 417, 418, 420, 425, 427, 428, 429, 431, 432, 436, 437, 439, 440, 441, 442, 445, 446, 447, 448, 449, 450, 451, 454, 456, 457, 458, 459, 460, 461, 462, 466, 468.1, 468.2, 469, 472, 473, 474, 477, 478, 479, 481, 482, 483, 486, 490, 491, 500, 502, 503, 505, 507, 510, 512, 513, 515, 516, 518, 523, 531, 532, 546, 547, 550, 555, 556, 562, 564, 568, 569, 570, 576, 585, 587, 588, 589, 590, 597, 598, 599, 600, 601, 603, 607, 608, 609, 618, 619, 676, 680, 685, 686, 687 & 826\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\n65\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWorks Nos. 4A, 4B and 4C\n104, 105.1, 105.2, 105.3, 110, 111.1, 111.2, 120, 121, 122, 123, 126, 127, 129, 130, 133, 153, 156, 159, 160, 161, 162, 165, 169, 172, 175, 176 & 177\nConstruction of authorised development\nWork No. 4A\n131, 140, 141, 148, 163, 166, 167, 170, 181, 182 & 184\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4A\n173, 178, 179, 180, 185, 186, 192 & 193\nDismantling of redundant infrastructure\nWork No. 4A\n183\nDismantling of redundant infrastructure\nWork No. 4A\nRemoval of pylon foundations only to a depth of 1 metre\n256, 266, 273, 275, 276, 326, 327, 328, 330, 331, 470.1, 470.2, 471.1, 471.2, 475, 476, 480, 488, 489, 493, 495, 549, 551, 552, 563 & 565\nConstruction of authorised development\nWork No. 4B\n624, 702, 703, 704, 707, 759, 760, 762, 772, 782.1, 782.2, 783, 784, 785, 816, 817, 833, 976.1 & 976.2\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWorks Nos. 4B and 4D\n625, 628, 629, 630, 636, 660.1, 660.2, 660.3, 660.4, 660.5, 661, 662, 663.1, 663.2, 664, 665, 666, 667, 668, 669, 768, 786, 787, 788, 789, 790, 791, 792, 793, 794, 795, 796, 797, 798, 799, 800, 801, 802, 803, 804, 805, 806, 807, 808, 809, 810, 811, 812, 813, 814, 836, 837, 838, 839, 840, 841, 842, 843, 844, 845, 846, 847, 848, 849, 850, 851, 852, 853, 854, 855, 856, 857, 858, 859, 860, 861, 862, 863, 864, 865, 866, 867, 868, 869, 870, 871, 872, 874, 875, 876, 877, 878, 879, 880, 881, 882, 884, 885, 886, 906, 908, 909, 910, 911, 912, 913, 914, 915, 916, 917, 918, 919, 920, 921, 922, 923, 924, 925, 926, 927, 928, 929, 930, 931, 932, 933, 934, 935, 936, 937, 938, 939, 943, 944, 949, 950, 951, 952, 953, 954, 955, 956, 957, 958 & 959\nDismantling of redundant infrastructure\nWork No. 4D\n626.1, 626.2, 627, 634, 635, 637, 643, 648, 649, 658, 659, 723, 729, 731, 737, 739, 740, 741, 742, 743, 744, 745, 748, 750, 752, 753, 754, 818, 829, 831, 834, 887, 888, 889, 945, 946, 948, 978, 979 & 980\nConstruction of authorised development\nWork No. 4D\n631, 633, 670, 769, 835, 873 & 907\nDismantling of redundant infrastructure\nWork No. 4D\nRemoval of pylon foundations only to a depth of 1 metre\n632, 639, 640, 641, 642, 650, 651, 671, 905 & 960\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4D\n758\nConstruction of authorised development\nWorks Nos. 4B and 4D\n764, 765, 770, 777, 780 & 781.2\nDismantling of redundant infrastructure\nWorks Nos. 4B and 4D\n771, 781.1 & 815\nDismantling of redundant infrastructure\nWorks Nos. 4B and 4D\nRemoval of pylon foundations only to a depth of 1 metre\n981, 982, 987, 988, 989, 990, 991, 992, 993, 994, 1002, 1004, 1008, 1009, 1011, 1012, 1013, 1015, 1016, 1017, 1019 & 1020\nConstruction of authorised development\nWork No. 4F\n995 & 996\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4F\n999 & 1000\nDismantling of redundant infrastructure\nWork No. 4F\n1001\nConstruction of authorised development\nWork No. 4F\nRemoval of pylon foundations only to a depth of 1 metre\nNorth Somerset Council – Section E\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n1, 4, 6, 7, 33, 37, 40, 49, 50, 59, 60, 63, 132, 133, 138, 146, 149, 162, 163, 191, 194, 222, 232, 238 & 239\nConstruction of authorised development\nWork No. 4D\n10, 34, 43, 46, 53, 94, 103, 104, 109, 110, 112, 113, 154, 167 & 176\nConstruction of authorised development\nWorks Nos. 4B and 4D\n11, 16, 19, 29 & 93\nDismantling of redundant infrastructure\nWorks Nos. 4B and 4D\n13, 14, 68, 70, 77, 79, 105, 127, 128, 135, 136, 145, 159, 168, 169, 170, 174 & 175\nDismantling of redundant infrastructure\nWork No. 4B\n23, 30, 45, 54 & 66\nDismantling of redundant infrastructure\nWorks Nos. 4B and 4D\nRemoval of pylon foundations only to a depth of 1 metre\n44, 57, 65, 96, 116 & 120\nDismantling of redundant infrastructure\nWork No. 4D\nRemoval of pylon foundations only to a depth of 1 metre\n78, 126, 142, 143, 155 & 171\nDismantling of redundant infrastructure\nWork No. 4B\nRemoval of pylon foundations only to a depth of 1 metre\n95.1, 95.2, 97, 98, 99.1, 99.2, 100.1, 100.2, 101, 115, 119, 207, 208, 209 & 210\nDismantling of redundant infrastructure\nWork No. 4D\n117, 118, 121, 122, 123, 134 & 144\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4D\n160\nConstruction of authorised development\nWorks Nos. 4B and 4D\n131, 137, 172 & 173\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\nNorth Somerset Council – Section F\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n1, 2, 3, 4, 18, 19, 21, 22, 23, 29, 30, 34, 35, 36 & 202\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4B\n5, 6, 7, 8, 10, 11, 12, 13, 14, 15, 16, 17, 24, 25, 26, 27, 31, 32, 33, 138, 139, 140, 141, 142, 143, 144, 145, 146, 149 156, 158, 159, 219.1, 222, 224, 225, 228 & 229\nDismantling of redundant infrastructure\nWork No. 4B\n9, 20, 28, 37, 157, 201 & 219.2\nDismantling of redundant infrastructure\nWork No. 4B\nRemoval of pylon foundations only to a depth of 1 metre\n38, 40, 41, 45, 60, 160, 161, 162 & 165\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4D\n39, 64, 79, 81, 200, 218 & 249\nDismantling of redundant infrastructure\nWork No. 4D\nRemoval of pylon foundations only to a depth of 1 metre\n43, 67, 95, 98, 137, 176, 177, 178, 179, 186, 188, 192, 194, 196, 213 & 217\nConstruction of authorised development\nWork No. 4D\n46, 47, 48, 57, 58, 59, 69, 72, 74, 76, 78, 82, 83, 84, 88, 89, 90, 91, 150, 151, 152, 153, 154, 155, 166, 167, 168, 169, 170, 172, 199, 214.1, 214.2 & 223\nDismantling of redundant infrastructure\nWork No. 4D\n148, 163, 203 & 204\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWorks Nos. 4B and 4D\n226, 230, 231, 233, 247 & 248\nConstruction of authorised development\nWork No. 4E\n227\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWorks Nos. 4B, 4D, 4E, 4G and 4P\n232, 278, 298 & 320\nDismantling of redundant infrastructure\nWork No. 4G\nRemoval of pylon foundations only to a depth of 1 metre\n234, 235, 240, 243, 276, 282, 293, 302 & 304\nDismantling of redundant infrastructure\nWork No. 4G\n253, 255 & 285\nDismantling of redundant infrastructure\nWork No. 4P\n258\nDismantling of redundant infrastructure\nWork No. 4P\nRemoval of pylon foundations only to a depth of 1 metre\n260 & 264\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4P\n267, 269, 279, 280, 281, 288, 294, 296, 300, 307, 312, 314, 316, 317, 322, 326, 327, 328, 329 & 330\nConstruction of authorised development\nWork No. 4P\n284\nConstruction of authorised development\nWork No. 4P\nRemoval of pylon foundations only to a depth of 1 metre\n303, 313 & 325\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWorks Nos. 4G and 4P\nNorth Somerset Council – Section G\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n38, 39.1, 39.2, 42, 43, 45, 46, 47.1, 47.2, 48, 52,57, 58.1, 58.2, 59, 64, 69, 84, 107, 118, 134 & 137\nDismantling of redundant infrastructure\nWork No. 4G\n53, 61, 65, 108, 111, 116 & 138\nDismantling of redundant infrastructure\nWork No. 4G\nRemoval of pylon foundations only to a depth of 1 metre\n23.1, 23.2, 24.1, 24.2, 25, 82, 112, 113, 119, 120, 121, 122, 124, 125, 127, 128 & 130\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4G\nNorth Somerset Council and Bristol City Council – Section G\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n139\nDismantling of redundant infrastructure\nWork No. 4G\nBristol City Council – Section G\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n143, 144, 145, 146, 148, 151, 248, 249, 250, 251, 252.1, 252.2, 253, 254, 255, 256, 257, 258, 259, 262, 263, 264, 265, 266, 267, 268, 270, 271, 272, 273, 274.1, 274.2, 275, 276, 277, 278, 279, 280, 281, 282, 283, 284, 285, 286, 287, 288, 289, 290, 291, 292, 293, 294, 295, 296, 297, 298, 299, 300, 301, 303, 304, 305, 306, 307, 308, 309, 310, 311, 312, 313, 315, 316, 317, 318, 322, 323, 324, 325, 326, 327, 329, 330, 331, 332, 333 & 334\nDismantling of redundant infrastructure\nWork No. 4G\n147.1, 147.2, 260, 269, 302, 314 & 328\nDismantling of redundant infrastructure\nWork No. 4G\nRemoval of pylon foundations only to a depth of 1 metre\n261, 319, 320 & 321\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4G\n335\nDismantling of redundant infrastructure\nWorks Nos. 4G and 4H\nRemoval of pylon foundations only to a depth of 1 metre\n336\nConstruction of authorised development\nWork No. 4K\n337\nConstruction of authorised development\nWorks Nos. 4I and 4K\n338, 339, 340, 341, 342, 343, 344, 345, 346, 347, 359, 378, 437, 438, 439, 474, 475, 476, 477, 478, 479, 480, 481, 482.1, 482.2 , 498.1, 498.2 , 499, 500, 501, 503, 504, 514, 515, 517, 518 & 519\nDismantling of redundant infrastructure\nWork No. 4H\n351, 352.1, 352.2, 353.1, 353.2, 355, 380, 383, 384, 399, 400, 401, 402, 403, 404, 406, 407, 408 & 441\nConstruction of authorised development\nWork No. 4I\n397 & 409\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWork No. 4H\n398, 405, 440 & 502\nDismantling of redundant infrastructure\nWork No. 4H\nRemoval of pylon foundations only to a depth of 1 metre\n562 & 564\nConstruction of authorised development\nWorks Nos. 4M and 4N\n563, 570, 571, 572 & 575\nConstruction of authorised development\nWorks Nos. 4L, 4M and 4N\n565\nDismantling of redundant infrastructure\nWork No. 4N\n572\nConstruction of authorised development\nWorks Nos. 4L, 4M and 4N\n599\nDismantling of redundant infrastructure\nWork No. 4L\nRemoval of pylon foundations only to a depth of 1 metre\n604, 605, 606, 607, 609 & 610\nAccess to land for the purpose of carrying out the authorised development including the power to carry out any ancillary works necessary to facilitate that access\nWorks Nos. 4L, 4M, 4N and 4O\n608 & 611\nConstruction of authorised development\nWorks Nos. 4L, 4M, 4N and 4O\nSouth Gloucestershire Council – Section G\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n558 & 559\nConstruction of authorised development\nWorks Nos. 4M and 4N\n560\nConstruction of authorised development\nWorks Nos. 4L, 4M and 4N\n573\nConstruction of authorised development\nWork No. 4L\nBristol City Council and South Gloucestershire Council – Section G\n(1)\nPlot number of land shown on Land Plan\n(2)\nPurpose for which temporary possession may be taken\n(3)\nRelevant part of the authorised development\n(4)\nElement of Work in respect of which land is not required to be re-instated\n561\nConstruction of authorised development\nWorks Nos. 4M and 4N\n574\nConstruction of authorised development\nWork No. 4L",
  "extent": null,
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Words in Sch. 12 Pt. 2 substituted (21.7.2017) by The National Grid (Hinkley Point C Connection Project) (Correction) Order 2017 (S.I. 2017/786), art. 1, Sch."
    },
    {
      "type": "F",
      "label": "F2",
      "text": "Words in Sch. 12 Pt. 2 inserted (21.7.2017) by The National Grid (Hinkley Point C Connection Project) (Correction) Order 2017 (S.I. 2017/786), art. 1, Sch."
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2016/49/schedule/12/part/2",
    "retrieved_at": "2026-10-28T23:28:15.566000+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}