# The National Grid (Hinkley Point C Connection Project) Order 2016, Paragraph 3: Design drawings


(1) The authorised development must be carried out in general accordance with the design drawings.
(2) The authorised development will not be in general accordance with the design drawings to the extent that any departure from the design drawings gives rise to any materially new or different environmental effects from those assessed in the Environmental Statement.

---
Source: https://www.legislation.gov.uk/uksi/2016/49/schedule/3/paragraph/3 (the official version)
Page: https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016/schedule-3/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.