# The National Grid (Hinkley Point C Connection Project) Order 2016, Paragraph 45: England Coast path


(1) No works to—
(a) dismantle the existing overhead lines—
(i) between pylon VQ1 and VQ2, and
(ii) between pylon ZZ4 and ZZ5, and
(b) string the proposed new overhead lines—
(i) between pylon VQ3A and VQ3B, and
(ii) between pylon ZZ4 and ZZ5,
may commence until consent given by the relevant street authority in respect of the diversion of footpaths WL23/71 and WL23/61.
(2) The consent of the relevant street authority referred to in paragraph (1) must not be unreasonably withheld.

---