# The National Grid (Hinkley Point C Connection Project) Order 2016, Paragraph 16: Upon commencement of the works


The licence holder must ensure suitable bunding or storage facilities are employed to prevent the release of fuel oils, lubricating fluids and chemicals associated with vessels, plant and equipment into the marine environment.

---
Source: https://www.legislation.gov.uk/uksi/2016/49/schedule/9/paragraph/16 (the official version)
Page: https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016/schedule-9/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.