# The National Grid (Hinkley Point C Connection Project) Order 2016, Paragraph 18: Upon commencement of the works


Any construction materials that are misplaced below mean high water springs and cannot be recovered must be located and their position notified to the MMO Local Office and the MMO as deemed Licensing Authority within 48 hours.

---
Source: https://www.legislation.gov.uk/uksi/2016/49/schedule/9/paragraph/18 (the official version)
Page: https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016/schedule-9/paragraph-18
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.