# The National Grid (Hinkley Point C Connection Project) Order 2016, Paragraph 20: Upon commencement of the works


The licence holder must ensure that any equipment, temporary structures, waste and debris associated with the works are removed within 20 business days of completion of any of the works.

---
Source: https://www.legislation.gov.uk/uksi/2016/49/schedule/9/paragraph/20 (the official version)
Page: https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016/schedule-9/paragraph-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.