# The National Grid (Hinkley Point C Connection Project) Order 2016, Paragraph 9: Prior to the commencement of the works


The licence holder must inform the MMO and Environment Agency in writing of the intended start date and the likely duration of licensed activities on a site at least 10 business days prior to the commencement of the first licensed marine activity.

---
Source: https://www.legislation.gov.uk/uksi/2016/49/schedule/9/paragraph/9 (the official version)
Page: https://openlegislation.uk/national-grid-hinkley-point-c-connection-project-order-2016/schedule-9/paragraph-9