# The National Grid (King’s Lynn B Power Station Connection) Order 2013, Article 4: Development consent etc granted by the Order

Extent: E+W+S

(1) Subject to the provisions of this Order and to the Requirements the undertaker is granted development consent for the authorised development to be carried out within the Order limits.
(2) The undertaker may install, and keep installed, above ground the electric line included in the authorised development.
(3) The undertaker may operate and use the electric line and any other elements of the authorised development as part of the high-voltage electricity transmission system in England and Wales.
(4) Subject to article 6 (limits of deviation) the authorised development comprised in Work No 1 must be constructed and installed in the lines and situations shown on the works plans and in accordance with the levels shown on the sections.

---
Source: https://www.legislation.gov.uk/uksi/2013/3200/article/4 (the official version)
Page: https://openlegislation.uk/national-grid-kings-lynn-b-power-station-connection-order-2013/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.