# The National Grid (King’s Lynn B Power Station Connection) Order 2013, Article 6: Limits of deviation

Extent: E+W+S

In carrying out or maintaining the authorised development comprised in Work No 1 the undertaker may—
(a) deviate laterally from the lines or situations of the authorised development shown on the works plans to the extent of the limits of deviation shown on those plans, save for tower KL01 which must not deviate more than 4 metres in a northerly direction from the position indicated on the works plans; and
(b) deviate vertically from the levels of the authorised development shown on the sections—
(i) to any extent not exceeding 3 metres upwards; or
(ii) to any extent downwards as may be necessary, convenient or expedient.

---
Source: https://www.legislation.gov.uk/uksi/2013/3200/article/6 (the official version)
Page: https://openlegislation.uk/national-grid-kings-lynn-b-power-station-connection-order-2013/article-6
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.