# The National Grid (King’s Lynn B Power Station Connection) Order 2013, Paragraph 16: Construction hours

Extent: E+W+S

(1) Subject to sub-paragraphs (2) and (3) construction work must not take place other than between 0700 and 1900 hours, on any day, unless otherwise agreed by the relevant planning authority.
(2) Piling operations must not take place other than between 0800 and 1700 hours on Mondays to Fridays, unless otherwise agreed by the relevant planning authority.
(3) Protective netting of scaffolding and its subsequent removal across highways and the King’s Lynn to London railway line must occur outside of the construction working hours.

---
Source: https://www.legislation.gov.uk/uksi/2013/3200/schedule/2/paragraph/16 (the official version)