(1) No stage of the authorised development is to commence until a written scheme for the management and mitigation of dust emissions has been submitted to and approved by the relevant planning authority in relation to that stage.
(2) The approved scheme for the management and mitigation of dust emissions must be implemented before any stage of the authorised development can commence, and maintained during the construction, operation and decommissioning of the authorised development.

---