(1)
(2)
(3)
Area
Number of land shown on land plan
Purpose for which temporary possession may be taken
Borough of King’s Lynn and West Norfolk
Plots 1, 4, 6, 8, 18, 20, 24, 33, 36, 42, 53, 53a, 53b, 55, 55a, 57, 66 and 66a
Installation of the authorised development (comprised within Class 1 new rights specified in the book of reference)
Plots 65a, 65b, 65c, 67, 67a, 67b, 68, 68a, 68b, 69, 69a, 69b, 70, 71a, 72, 72a
Installation incidental to and to facilitate the authorised development (comprised within Class 5 new rights specified in the book of reference)
Plots 1, 2, 3, 4, 5, 6, 7, 8, 9, 10, 11, 12, 13, 15, 15a, 16, 17, 18, 19, 20, 23, 24, 26, 30, 31, 32, 33, 34, 35, 36, 41, 42, 48, 49, 49a, 51, 51a, 51b, 52, 52a, 52b, 53, 53a, 53b, 54, 54a, 55, 55a, 56, 57, 65, 65c, 65d, 66, 66a, 67, 68, 69, 70 and 72
Construction associated with the installation of the authorised development (comprised within Class 2 new rights specified in the book of reference)
Plots 14, 21, 22, 25, 27, 28, 29, 37, 38, 39, 40, 43, 43a, 44, 45, 46, 46a, 47, 50, 58, 58a, 58b, 59, 60, 61, 62, 63, 64, 65b, 71, 71a, 73, 74, 75, 76, 77 and 78
Access associated with the installation and construction of the authorised development (comprised within Class 3 and Class 7 new rights specified in the book of reference)
Plots 67a, 67b, 68a, 68b, 69a and 72a
Access incidental to and to facilitate the installation of the authorised development (comprised within Class 7 new rights specified in the book of reference)
Plots 1, 2, 3, 4, 6, 7, 8, 49, 51, 51b, 52, 52b, 53, 53b, 54, 55, 65, 65d and 66
Landscaping associated with the installation and construction of the authorised development (comprised within Class 4 new rights specified in the book of reference)
Plots 73, 74, 75 and 76
Scaffolding and temporary structures associated with the installation and construction of the authorised development (comprised within Class 6 new rights specified in the book of reference)
Plots 67a, 67b, 68a, 68b, 69a and 72a
Scaffolding and temporary structures incidental to and to facilitate the installation of the authorised development (comprised within Class 6 new rights specified in the book of reference)

---
Source: https://www.legislation.gov.uk/uksi/2013/3200/schedule/7 (the official version)
Page: https://openlegislation.uk/national-grid-kings-lynn-b-power-station-connection-order-2013/schedule-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.