# The National Grid (King’s Lynn B Power Station Connection) Order 2013, Paragraph 1: Applications made under requirement

Extent: E+W+S

Where an application has been made to the relevant planning authority for any agreement or approval required pursuant to a Requirement included in this Order, the relevant planning authority must give notice to the undertaker of their decision including the reasons on the application, within a period of 8 weeks beginning with—
(a) the day immediately following that on which the application is received by the authority; or
(b) such longer period as may be agreed by the undertaker and the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2013/3200/schedule/9/paragraph/1 (the official version)
Page: https://openlegislation.uk/national-grid-kings-lynn-b-power-station-connection-order-2013/schedule-9/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.