# The National Grid (King’s Lynn B Power Station Connection) Order 2013, Paragraph 3: Appeals

Extent: E+W+S

The undertaker may appeal in the event that—
(a) the relevant planning authority refuses an application for any consent, agreement or approval required by a requirement included in this Order or grants it subject to conditions; or
(b) the relevant planning authority does not give notice of its decision to the undertaker within the time period specified in paragraph 1;
and any appeal must be made within 42 business days following the occurrence of any of the events in sub-paragraphs (a) and (b).

---
Source: https://www.legislation.gov.uk/uksi/2013/3200/schedule/9/paragraph/3 (the official version)
Page: https://openlegislation.uk/national-grid-kings-lynn-b-power-station-connection-order-2013/schedule-9/paragraph-3
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.