# The National Grid (North London Reinforcement Project) Order 2014, Introduction: Introductory text

Extent: E+W+S

Infrastructure Planning
Made 16th April 2014
Coming into force 7th May 2014
An application has been made to the Secretary of State in accordance with the Infrastructure Planning (Applications: Prescribed Forms and Procedures) Regulations 2009 for an Order under sections 114, 115 and 120 of the Planning Act 2008 (“the 2008 Act”);
The application was examined by a single appointed person appointed by the Secretary of State pursuant to Chapter 3 of Part 6 of the 2008 Act, and the examination was carried out in accordance with Chapter 4 of Part 6 of the 2008 Act, and the Infrastructure Planning (Examination Procedure) Rules 2010;
The single appointed person, having considered the application with the documents that accompanied the application, and the representations made and not withdrawn, has, in accordance with section 83(1) of the 2008 Act, made a report and recommendation to the Secretary of State;
The Secretary of State, having considered the report and recommendation of the single appointed person, and decided the application, has determined to make an Order giving effect to the proposals comprised in the application with modifications which in the opinion of the Secretary of State do not make any substantial change to the proposals;
The Secretary of State, in exercise of the powers conferred by sections 114, 115 and 120 of the 2008 Act, makes the following Order:

---
Source: https://www.legislation.gov.uk/uksi/2014/1052/introduction (the official version)
Page: https://openlegislation.uk/national-grid-north-london-reinforcement-project-order-2014/introduction
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.